GBA Logo horizontal Facebook LinkedIn Email Pinterest Twitter X Instagram YouTube Icon Navigation Search Icon Main Search Icon Video Play Icon Plus Icon Minus Icon Picture icon Hamburger Icon Close Icon Sorted

Community and Q&A

Shear Wall Sheathing and Siga Wigluv tape over top plate

idahobuild | Posted in General Questions on

Hey all,

Shear wall table shows only that the 4×8 OSB shall be horizontal and blocked.  There is now a discussion about the minimum width of a piece being 24″x4’x8′.  Our architectural plans call for WIGLUV tape over the top plate of the 9 foot walls — between the top plate and the 18″ raised heel trusses.

Can we still have the sheathing separation between the bottom cords of the trusses and the top plate to allow for the tape to go in there?

GBA Prime

Join the leading community of building science experts

Become a GBA Prime member and get instant access to the latest developments in green building, research, and reports from the field.

Replies

  1. Expert Member
    Michael Maines | | #1

    It depends on how much uplift is acting on the trusses. In most cases, screws or other hardware are an adequate connection and the sheathing doesn't need to be continuous. When running the sheathing across the joint is preferable, I either tape from the top plate to the sheathing before the trusses are set, or use a flexible sealant such as Contega HF at the top plate/sheathing connection.