How to detail vertical edge with stepped foundation

PaulT6300 | Posted in Green Building Techniques on

We’ve build a building in Costal Maine. The exterior is copper flashing, advantex sheathing, house wrap, rain screen and cedar shake. The building sits on a sloped lot. The foundation steps down the slope leading to vertical section of the exterior build up that are exposed. How should we detail this to make it look finished and not impede water movement. What we’ve done to date is caulk the joint between the concrete and the other layers. We are considering running a trim board along the edge and leaving the horizontal edges open to allow the rain screen behind the shake to breath. We’ve used boral for the exterior trim and would presumably use the same here.

Thanks
Paul

GBA Prime

Join the leading community of building science experts

Become a GBA Prime member and get instant access to the latest developments in green building, research, and reports from the field.

Replies

  1. GBA Editor
    Martin Holladay | | #1

    Paul,
    In my opinion, finishing this transition with a piece of vertical trim would be much better than leaving the edges of the rainscreen product open to improve ventilation. The rainscreen will work fine, even if this vertical transition is trimmed with a 1x1.