GBA Logo horizontal Facebook LinkedIn Email Pinterest Twitter X Instagram YouTube Icon Navigation Search Icon Main Search Icon Video Play Icon Plus Icon Minus Icon Picture icon Hamburger Icon Close Icon Sorted

Community and Q&A

Exterior Wall Assembly Questions

VTLiving | Posted in General Questions on

We are in the final stages of designing our above-grade exterior wall assembly for what we hope will be a “pretty good house” in central Vermont, and would be grateful for additional advice (previous post responses have been so helpful).  Our builder is not familiar with high-performance installations.  We currently have in mind the following layers, from the outside in:

1) Metal or composite board-and-batten style siding (likely vertically oriented)

2) Rainscreen

3) 1/2″ ZIP sheathing, taped

4) 7.5-inch “composite” studs, comprised of 2×6’s with ripped strips of 2″ ZIP-R tacked to the inside, to provide an R10 thermal break, with 7.25-inch rockwool batting in cavities [this is basically the Bonfiglioli wall, but using Zip-R instead of the homemade strips — our architect uses this a lot]

5) Intello Plus smart vapor barrier

6) 2×4 studs, with 3.5-inch rockwool batting in cavities.  Our architect typically specs strapping here, but the extra wall protects the Intello, gives us extra insulation, and also to make electrical, plumbing, drywall easy, so it seems like a good idea (?).

7) drywall

8) ordinary paint

Our primary question is whether we should worry about the air gap resulting from having 7.25-inch rockwool batting in 7.5-inch deep cavities — and, if so, what we might do about it?  I would expect we would place the air gap immediately behind the intello.  If it is a problem, one possible solution we considered is to use 1.5″ ZIP-R to make a 7.0-inch cavity, and put two layers of 3.5″ rockwool in there.  

A secondary question: what would be the best way to construct the rainscreen in this case?  We’ve heard diagonal stripping can be used for vertical siding.  Cor-A-Vent will, of course, be substantially more expensive, but is on the table.  The 1.5-inch bidirectional strapping behind the siding, seems like a lot of extra work over diagonal or Cor-A-Vent, and also makes the wall much thicker and adds some complexity to doors/windows.

Thank you all very much!

GBA Prime

Join the leading community of building science experts

Become a GBA Prime member and get instant access to the latest developments in green building, research, and reports from the field.

Replies

  1. Expert Member
    Akos | | #1

    Small gaps like that on the warm side of insulation are inevitable and generally don't effect performance.

    With doublestud wall, the thermal break comes from the offset studs of the service cavity. Doing the Bonfig stud doesn't change the assembly R value all that much, not sure if it is worth the effort.

    Generally you do one or the other, not both. That is bump up the studs 2x8 with foam strips and insualte with batts and no service cavity or 2x8 +2x4 stud double stud wall.

    Most metal panels have enough grooves as part of the profile for some amount of air flow. The ones I've installed before, I used horizontal strapping only.

    For regular board and batten, you can also put vertical strapping under each batten. You can also use larger cement board panels over vertical strapping and finish them with battens for a B&B look.

    You can also do reverse board and batten as now the battens becomes the rain screen strapping. Fussier install as you have to get the spacing even, no hiding uneven gaps under battens.

  2. FrankD | | #2

    A 7.25" batt will easily fluff up to fill a 7.5" space or compress into a 7" space. I agree with Akos on the Bonfiglioli approach. By itself it is a strategy worth considering,. Buried in a double-stud wall, the marginal gain over 2x8 studs will be very very small.

  3. matthew25 | | #3

    That is a ton of expensive rockwool. Why not use blown cellulose or fiberglass? With the depth of wall you have, that is going to be a high-performing and low-cost option. Also way lower embodied carbon if you care about that kind of stuff.

  4. begreener | | #4

    As others have suggested, I think using staggered studs to deal with thermal bridging is the way to go here ...

    The only other thing you might consider for the service cavity is potentially using a lightweight steel stud that already has electrical knockouts

    They come in a variety of dimensions:

    1 5/8-inch width
    2 1/2-inch width
    3 5/8-inch width

Log in or create an account to post an answer.

Community

Recent Questions and Replies

  • |
  • |
  • |
  • |