Do you need a 1/8th expansion gap in your roof sheathing when you have 16 o.c. Framing? This is on an unvented 1:12 slope roof with metal panels. Closed cell spray foam will go on inside of roof sheathing if that matters.
GBA Detail Library
A collection of one thousand construction details organized by climate and house part
![](https://www.greenbuildingadvisor.com/app/themes/greenbuildingadvisor/dist/img/modules/detail-library/thumb1.png)
![](https://www.greenbuildingadvisor.com/app/themes/greenbuildingadvisor/dist/img/modules/detail-library/thumb2.png)
Replies
MHunt11,
The gap is not dependent of the spacing of the framing. All that affects is whether you need mid-span supports (like H-clips) or not. Yes you need to leave an expansion gap of 1/8". Many large sheet goods suppliers, like Weyerhaeuser, size their sheets accordingly.