Communicate with subs prior to getting bids?
New Construction, Zone 4b, 50″+ precipitation
In addition to structural details on my plans, I am adding a whole page dedicated to emphasizing the priority of an airtight envelope. All details related to air barrier, flashing, wrb, and insulation, with exploded views in many cases.
I want to add a “Project Note to All Trades” on this page. I am asking for suggestions for what it should say.
For example: “All penetrations in the envelope must have prior approval by the builder.”
Suggestions?
GBA Detail Library
A collection of one thousand construction details organized by climate and house part
Replies
Look for a builder with experience in building energy efficient housing.
I wrote a series of columns on GBA that cover management of trade contractors: https://www.greenbuildingadvisor.com/blogs/dept/business-advisor/trade-contractor-management-creating-programs-work
When I was a contractor I created a checklist management system that we used in my company. You can download it for free as a GBAPro member or purchase it from me - links are at the end of each of the articles in the series. Between the articles and the checklists you should find a good selection of ideas for your project.
Your checklists are very helpful. Articles will be consumed with coffee when I have a moment. Certainly worth the price of admission! Thanks Carl.