Overview of Panelized Construction

A look at the benefits, manufacturing and delivery methods, and potential pitfalls of prefabricated building enclosures

Tight control over the environmental conditions when building is one of the benefits off-site panelization.

Panelized construction describes walls, floors, and roofs built in a factory and then transported to the project site where they are lifted with a crane and set on a foundation. A crew typically provided by the panel company joins the panels together to create a fully watertight and airtight building enclosure. Different panel manufacturers provide different components and assemblies, but most high-performance panelizers include the structural framing, sheathing, and water, vapor, and air control layers. Often, insulation is included and installed at the factory; some manufacturers install rainscreen battens, flashing, and windows as part of the panelization package. All of the panelized house packages I’m familiar with include the exterior and load-bearing components. Sometimes interior walls are included, sometimes not. Interior and exterior finishes are generally done by others.

Local and national panelization companies are now routinely producing high-quality, energy-efficient building enclosures that anyone can buy and have assembled on their site to speed a construction project. A few years ago, our company, Birdsmouth Design-Build, was involved in an 11-home development where we used panelized construction (See Building a Zero-Energy Home for Less). More recently we used panels from a different panel manufacturer to build a 2224-sq.-ft, single-story custom home in Portland, Oregon. These experiences, along with travel to panel manufacturers in the United States and Europe, have given me insight into this brave new world of “off-site” construction.

Why panels?

The biggest benefit of a panelized house is the reduced time it takes to get from foundation to watertight building, which can happen in days or weeks versus months for traditional stick framing. The ideal scenario allows for quicker occupancy and reduced costs related to overhead, such as insurance, project management, and interest and fees paid on construction loans. This shorter time frame is also ideal for projects in rural locations where labor is scarce or where winter or wet weather can create challenging building conditions. Building with panels can also allow a contractor to complete more projects with a smaller team.

Since the panels are built in a controlled environment by well-trained workers using back- and labor-saving tools, panel producers say there is less potential for errors or compromise. For a builder or homeowner located in an area with a limited number of contractors focused on high-performance construction, going with panels can ensure a high-quality enclosure that meets their goals for durability, safety, and energy efficiency. Proponents of panelization will point to economies of scale that can be reached by ordering large quantities of material and purchasing when lumber and sheathing prices are lower.

My experience is with a pair of custom builds, but many panelization companies offer standard plans in a wide variety of house sizes. With the design work complete and the added efficiency of a home that can be built many times, they can be less expensive than a fully custom home; but beware that changes—even small ones—cut significantly into the savings.

Factory assembled

Built in a well-lit, climate-controlled factory, wall, roof, and floor panels are assembled on waist-high tables. Panel construction is based on detailed shop drawings. High-performance panels differ slightly by manufacturer, but generally have 2×4 or 2×6 sheathed structural walls with provisions for air, water, and vapor control. Like the Ecocor walls shown in the photos, the walls on our most recent project used I-joists as Larsen trusses to create an insulation cavity.

Image of someone filling the cavity of a wall of a panelized house
Once the water-resistive barrier (WRB) and furring are attached to the I-joists, the exterior cavities are filled with cellulose insulation. Every cavity is drilled with a hole saw and then a worker with a high-pressure insulation blower dense-packs the space between I-joists. Photo: Patrick McCombe

Special logistics

Building with panels requires space for off-loading and machinery to lift the panels from the delivery truck and place them on the foundation.

Photo of panels being loaded off of a truck
Panels are delivered by semi-trucks with flatbed trailers. The combined length of the truck and trailer can reach 76 ft. long, which means you may need to find a nearby spot to offload the panels onto smaller trucks.
Panels being placed with a crane
Panels weigh hundreds of pounds each and are 8 ft. to 16 ft. long, so crane service is required to lift and place them. We hired a 5-ton crane for three days to lift and place the wall and roof panels on this build.

A quick path to a building shell

With much of the work done at the panel factory, an air- and watertight building shell can be completed in days instead of weeks or months. The foundation and any in-ground water management, plumbing, and electrical must be complete before the panels can be placed.

A crew of three placing wall panels on the foundation of a panelized house
Panels are lifted from the stack and placed one at a time following snapped layout lines. The crane holds each panel upright until it can be fastened to adjacent panels and braced.
A worker connecting wall panels with a drill
To maintain the correct building dimensions and create continuous air and water control, the panels must fit tightly together. Assembly crews use turnbuckles and large C-clamps to close gaps between panels as they’re installed. Photo: Patrick McCombe
Two images depicting bracing the panel walls
Wall panels must be made plumb and then securely braced before roof or floor systems can be installed. Any holes in the WRB, which can occur during panel installation and during later parts of construction, must be repaired with methods approved by the panel manufacturer.
Two images depicting sealing wall panel seams
Flexible sealant and building gaskets prevent air and water leaks between and around panels. Panel seams are then taped or sealed to complete the WRB. Photos: Patrick McCombe

Details make a sturdy structure

Panelized construction requires the same attention to detail as conventional residential construction. You may have to brief local inspectors who are likely to be unfamiliar with the panelized-build process.

A person connects metal straps to the panels
Metal straps join panels and offer resistance to wind and seismic forces. Details vary with each project, so check the construction documents for specific connection details and confirm installation crews are following the plan.
A person drilling anchor bolts through the panel into the foundation
It would be nearly impossible to match cast-in-place anchor bolts in the foundation to drilled holes in the factory-built wall panels, so concrete anchors or screws connect the panels to the foundation. The design should include the anchor type, size, and locations. Photo: Patrick McCombe
A large penetration hole in the wall panel
The locations and construction details for duct, plumbing, and electrical penetrations through the enclosure should be included in the design and the details should be consistent with the panel factory’s methods. Don’t forget penetrations for the ERV, range hood, and range hood’s makeup-air inlet.
Adding the air barrier to the roof
Roof panels are often framed with I-joists sheathed with 1⁄2-in.-or-thicker plywood or OSB and include a waterproofing membrane as temporary roofing. On our projects, the joist cavities were shipped uninsulated for assembly and wiring rough-in; we had to insulate and complete the air barrier on the ceiling. Panels can accommodate any roof pitch or geometry—this low-slope roof has a PVC membrane over pre-sloped EPS foam.

The rest of the build is the same

Using panels is a quick way to get a building shell up and dried in. However, the rest of the build is business as usual with the regular lineup of subs and work days required to finish the home’s interior and exterior.

Battens and barrier around a window
Before siding, the GC must finish detailing the enclosure. On the pictured project, we finished the water-management details around the flangeless windows and doors and the roof-to-wall transition, and leveled the 1⁄2-in. out-of-plane battens. This took two carpenters 80+ hours.
Ducting in the roof cavity
Our panelized builds keep ducts and all HVAC equipment inside the home’s conditioned space for efficiency. Our regular HVAC contractor installed the HVAC and ERV systems, which were sized and designed by Energy Vanguard, Dr. Allison Bailes’s engineering firm focused on indoor-air quality and home performance.
Wiring elements in exposed wall panels
The stud walls on the inside of wall panels and the I-joist cavities common to high-performance roof and floor panels make line and low-voltage wiring rough-in nearly the same as in a typical stick-framed build, with the same flexibility of outlet and fixture placement. Electrical inspections on our two projects were done by local inspectors.
Plumbing rough-in
On our panelized projects, supply and waste plumbing were installed by one of our regular plumbers. Plumbing and occupancy inspections were done by our regular building inspector.
Complete panelized house with dark siding
Once complete, panelized homes are indistinguishable from stick-built custom homes. Although many high-performance panelized houses have a modern aesthetic, panelized homes can be built in any architectural style.

Potential problems

Just because panels are made in a factory doesn’t guarantee they’re made well. We’ve seen errors in construction, panels made with low-quality framing lumber, and generally sloppy work. Thankfully our most recent build had high-quality lumber and the panels were built to within 1⁄8 in. of the shop drawings. The difference in quality can be night and day, so always ask for references from the panelization company you’re considering.

Panelization saves time, but only with the enclosure part of the build. In our experience, the rest of the build takes just as long as conventional construction. For our 12-month build, two months were dedicated to the enclosure, and we were able to slash a month off that part of the schedule and save one month in the overall build. However, in the weeks leading up to the panel delivery, we spent dozens of hours on scheduling and design, reviewing shop drawings with the panel manufacturers, architect, and clients. The result was less time spent building the enclosure, but perhaps an equal time spent on the phone and computer beforehand.

Coordination is also critical. If a site and foundation aren’t ready and the panel manufacturer has to reschedule a delivery, a delay of a few days can turn into weeks or months waiting for trucking companies or installation crews to reschedule. The site must also have the necessary access for staging panels and the site and access roads must accommodate heavy trucks.

Unforeseen things can go wrong too. After coordinating our delivery with the transportation company, at the last second they were unable to get a lowboy trailer for one of the shipments, and a taller trailer was too tall for the driveway. Luckily, there was an empty lot located about half a mile down the road where we could park two tractor trailers to move the panels from the higher trailer to the lower one for final delivery. Even then, there were times it looked like the truck and crane would get stuck going up the steep gravel driveway.

Cost savings can be elusive

Panelized projects should theoretically cost less because they’re built faster, which means fewer carrying costs. But one thing we have not found with panels is a cost savings on the overall build. We’ve found the economies of scale offered by factory production are eaten up by the costs of getting the panels to the site. Crane service for moving and placing the panels is expensive, too, and bringing in the crane and heavy delivery trucks may  involve moving overhead wires, cutting trees, or widening or strengthening driveways.

There also can be unanticipated carpentry expenses. Even when interior walls are included, the builder is often responsible for blocking for trusses, stairs, and attached structures like decks and porches. Additionally, some work such as completing the air barrier needs to be done by the general contractor after the panel crew leaves, such as installing membranes prior to installing dense-pack insulation. There may be engineering costs to satisfy local code officials that aren’t needed for a stick-framed build. Since the panels are produced off-site, getting inspections for things such as shear walls, nailing patterns, straps, or insulation can be tricky. Most panel manufacturers are aware of these requirements and have ways to verify with local inspectors that these tasks are being done to code. That said, not all jurisdictions accept photos of nailing patterns or insulation amounts from the panel factory.

On our most recent project, inspections for “manufactured housing” are arranged through the state. This process complicated things to such a degree that we didn’t think we’d be able to build the home. Luckily for us, the panel manufacturer, Collective Carpentry of Ivermere, B.C., was able to register with the state and satisfy some high hurdles in order to meet the requirements.

A path to high performance

A good panel manufacturer can help you build to performance standards like net-zero or Passive House. However, if you’re trusting the panel manufacturer to meet your airtightness goals, make sure your contract specifies the airtightness numbers and when the blower door test(s) will occur. Keep in mind that panel manufacturers may supply panels in several climate zones; to standardize their construction, the insulation amounts satisfy the most challenging climate zone where they do business. If the house is in a warmer climate zone, the panels may have more insulation and therefore be more expensive than necessary.

Our most recent panelized project was dried in within two-and-a-half days, with another day installing hardware and completing the air and water control layers. It’s a tight building: Our first blower door test with the windows and doors installed came in at 0.028 cfm per sq. ft., which is lower
than the Phius (prescriptive) target of 0.04.

If you’re considering a panelized build, my advice is to design the building with panels in mind. Ideally, you should choose the panelization company and their wall and roof assemblies during the early design decisions to maximize the efficiencies of using panels. Be sure to find a company that is well-organized and communicative as this plays a large part in crafting a successful project.

________________________________________________________________________

Josh Salinger is CEO and founder of Birdsmouth Design-Build, located in Portland, Oregon. Photos by Asa Christiana, except where noted. This article was originally published in Fine Homebuilding magazine, issue #321.

4 Comments

  1. Malcolm_Taylor | | #1

    Josh,

    Thanks for this. Too often articles on new or unconventional building techniques are written by proponents who downplay any drawbacks. It's great to hear for someone with a lot of experience who can give an even handed overview like this.

    1. Expert Member
      Joshua Salinger | | #3

      Thanks, Malcom. I very much wanted to reflect the true and sometimes messy reality of panelization and let folks take the information and do what they will with it. My direct experience of the two projects I have now done with panels is that both of them were significantly more expensive than if they were stick framed. In fact, if I had let my personal experience cloud the article, it would likely have been pretty unflattering for panelization. There are certainly times when it makes sense, don't get me wrong, but for an experienced high performance builder in a big enough market I am strained to see how it really makes financial sense.

      1. Malcolm_Taylor | | #4

        Josh,

        My only experience with them as a designer was much the same. They were expensive, and the advantages of quick assembly on site, were offset by the lead time required to get them there. I'm sure builders who use them regularly have things dialed in better. I think Michael Maines may be one of them.

  2. shtrum2 | | #2

    Excellent article and beautiful home. I concur about the importance of including warts and all . . . I remember when SIPs were getting big a few decades ago and people thought this meant incredible savings. We designed a home for an older couple relocating to hill country in North Carolina and the husband wanted SIP construction. I knew any savings would depend on simplicity of design so I developed a simple rectangle with a single sloped roof, with the plan bisected by an upended rectangle to be skylit and offering a framed glassy view down the mountainside straight from the entry. The bisected portion split the house into public (kitchen, living, dining) and private sides (bedrooms), with an open plan on the public side. When the wife saw it she wasn’t happy; she expected something much more traditional, involving multiple peaked roofs and a form that was problematic. I tried coming up with other options but nothing worked and we eventually parted ways. That was 20+ years ago and I never found out if they ever built their dream home, but I’m haunted by this design now.

    And yes, I’m still bitter . . . :)

Log in or create an account to post a comment.